Home : Alborz Turbine News : Alborz Turbine’s accomplishment as the Leader of Mapna Group Consortium in overhaul of Khalij Fars Power Plant
Alborz Turbine’s accomplishment as the Leader of Mapna Group Consortium in overhaul of Khalij Fars Power Plant

This "long-term contract for spare parts supply and overhaul of 6 gas units of ALSTOM GT 13 E2 " was awarded to the consortium of MAPNA Group (contractor), by Khalij Fars Power Production Management Co.. This consortium consists of MAPNA, Parto and Mavadkaran companies and is led by Alborz Turbine. This contract has been successfully accomplished with the effort of our expert colleagues and partners in the shortest time with the highest quality with the following highlights:

-          Units 1 to 6 were all handed over on time; Units 1, 2, 3, 5, 6 were delivered permanently after obtaining the Factory Acceptance Tests.
-          Unit 4 of this power plant, which was provisionally delivered on May 2nd 2017 is currently on guaranty period.
-          We are proud to note that the first set of Parto company’s domestic products, Vane stg 4 and Blade stg 5, which were installed on February 2017, are now operating without problems.